A Brief Colonial History Of Ceylon(SriLanka)
Sri Lanka: One Island Two Nations
A Brief Colonial History Of Ceylon(SriLanka)
Sri Lanka: One Island Two Nations
(Full Story)
Search This Blog
Back to 500BC.
==========================
Thiranjala Weerasinghe sj.- One Island Two Nations
?????????????????????????????????????????????????Monday, August 29, 2016
The ‘Yahapalana method’ of doing things: Crooked machinations in Rs. 60 billion coal tender
By C. A. Chandraprema-August 28, 2016
It
was only since last year that people have gradually become aware that
the supply of coal to the Norochcholai power plant is by far the
country’s biggest single tender worth more than Rs. 60 billion for a
three years’ supply of 6.75 million metric tonnes. On 18 June 2014, a
tender was floated to procure three years’ supply of coal. The price of
coal fluctuates and in order to ensure a constant supply at a fixed
price the government adopted the practice of giving out three-year
supply contracts. The tender procedures took several months and by that
time, a new government was in power. The new government seemed
determined that the tender should go to a new party and not to the
company that had been the main supplier of coal since the inception of
the Norochcholai power plant.
The contention of the new government was that one company had been
supplying coal since the Norochcholai plant began operations and that
Nobel Resources Ltd had somehow been bagging the contract every time.
Needless to say this huge contract gave rise to a great deal of
competition between the bidders, each leaving no stone unturned, no
appeal unmade, no court unmoved, in order to win the contract. From the
first tender onwards, Nobel Resources had emerged as the most successful
competitor being able to bag the contract even if it did not win in the
first round by putting in appeals and pleading its case in every
available forum. Even with regard to the tender floated on 18 June 2014,
despite an unprincipled effort by the yahapalana government to award
the tender to another company, Nobel Resources appealed successfully to
the Procurements Appeal Board saying that the rival company Swiss
Singapore Ltd had been given the contract after altering the bidding
criteria.
The Procurements Appeal Board recommended the cancellation of the tender
and calling for fresh bids. However, the new government brought a
cabinet paper to override the recommendation of the Procurements Appeals
Board and to award the tender to Swiss Singapore Ltd. The cabinet paper
recommended that a long term contract for the supply of 4.5 million
metric tonnes be awarded to Swiss Singapore Ltd at USD 68.72 per metric
tonne and for the procurement of 2.25 million metric tonnes of coal on
the spot tender procedure through the Standing Cabinet Appointed
Procurement Committee. Nobel Resources Ltd filed a fundamental rights
case against the Minister of Power and Renewable energy and the whole
Cabinet saying among other things that cabinet bad been misled into
approving the cabinet paper at issue.
Noble Resources International Pte Limited v Minister of Power and
Renewable Energy et al, became a landmark case because the Supreme Court
heard it as a matter of national interest despite arguments by the
Minister of Power and Renewable Energy and other respondents that the
Petitioner did not have the locus standi to invoke the jurisdiction of
the court because it was a foreign company acting on its own without a
local agent.
Chief Justice K. Sripavan stated that the court had decided to go into
the merits of the case as some of the events that took place in the
award of this tender ‘shocks the conscience of the Court’. Nobel
Resources had said in their petition to the Supreme Court that the
tender criteria had been altered after the bids had been opened.
First the cudgel
The bidding criteria were changed after the bids had been opened not
under the Rajapaksa government but under the present government that
came into power promising good governance. Hence what had ‘shocked the
conscience’ of the Supreme Court was not crookedness of the previous
government but that of the present one. The supreme court observed that
the Standing Cabinet Appointed Procurements Committee had received a
letter dated 29.06.2015 from Swiss Singapore Ltd and a meeting of SCAPC
was convened on the same day and they directed the Technical Evaluation
Committee to re-evaluate the Bids ignoring two steps of the Evaluation
Procedure. The lower granular size limit was among the two criteria
removed from the bidding documents so that more powdery coal would be
accepted. Swiss Singapore Ltd was thereupon awarded the tender by the
SCAPC.
The Supreme Court observed that ‘no one, neither the State nor the SCAPC
shall act contrary to the bid documents and the Government Procurement
Guidelines’ and stated that the Standing Cabinet Appointed Procurements
Committee should have rejected the bid of Swiss Singapore Ltd for
influencing the tender procedure. The SC stated very clearly that ‘the
decision made by the SCAPC was outside its jurisdiction and therefore
null and void’ and further that the decision taken by the Cabinet of
Ministers on 22 September 2015 to award the contract to Messrs Swiss
Singapore Ltd ‘could not be considered a valid decision’. One would
think that after an unequivocal statement from the Supreme Court like
that, the government would back down and cancel the tender and call for
fresh bids. But, what the government did was exactly the opposite. It
tried to justify before the public the retention of Swiss Singapore Ltd
as the coal supplier.
The first step in this was for the Minister of Power of Renewable energy
to appoint a Committee to look into the question whether the government
has suffered any monetary loss due to the way coal was purchased after
the present government came into power. The committee was appointed on
12 July 2016 and comprised of K. K.Y. W. Perera, Lakshman R.Watawala and
Janaka B. Ekanayaka. The committee observed that during 2015, there had
been two kinds of coal procurement - main long term bulk tender and
spot tenders for immediate procurements as per the cabinet decision
mentioned earlier. On this basis, 1,126,805 tonnes of coal had been
bought on four spot tenders after the cabinet decision up to 5 April
2016 at a cost of USD 56,075,563. Under the long term tender, 1,064,724
tonnes of coal had been purchased for USD 57,932,356. The average cost
of coal was USD 49.76 under spot tenders. While it was 54.41 under the
long term tender.
The Perera committee decided that there had been a total gain of 7.6
million USD from spot tenders as against the long term tender. The
report observes that spot prices depended on day-to-day market
conditions and that in 2016 there had been a slight upward trend in coal
prices and that there should be a balance between the spot purchases
and long term supply. The Perera committee report observes that the
original price quoted by Swiss Singapore Ltd was USD 68.72. Later it was
decided to change two of the bidding criteria. The index used was
changed from the Australian index to the South African index and it was
decided not to consider the grain size when purchasing the coal. After
further negotiations with Swiss Singapore on the basis of the changed
criteria, the price was reduced to USD 58. All other criteria such as
the ash content, the moisture content, volatile matter and sulphur
content were the same.
Noble Resources had quoted for coal with the particle size below 2 mm
being 10% or less while Swiss Singapore had put in bids to supply coal
where the grains below 2mm was as high as 25%. The Perera committee
observed that the ash content, moisture content, volatile matter and
sulphur content had a bearing on the operation of the coal power plant,
but the size of the granules had only a minor role to play in plant
efficiency. If the size of the coal is too large a separate crusher had
to be used to crush the coal. However, if coal particles were too small
below 2mm, it behaved like dust. When stocked in the coal yard this coal
would blow away with the wind and settle on nearby houses and trees.
The probability of self ignition in storage increases in the case of the
smaller particles. The Perera committee itself recommended that the
powdery coal dust had an environmental impact which was ‘not
quantifiable’ and that the amount of fine particles in the coal supplies
had to be controlled. By making this recommendation, the Perera
committee was in fact saying indirectly that the step that the
yahapalana government took to disregard the granular size of the coal in
order to award the contract to Swiss Singapore Ltd was wrong.
Then sweet talk
The Perera committee observed that the quality of each coal shipment
differs and that Swiss Singapore had delivered 18 coal shipments after
the removal of the penalties for granular size and the amounts actually
paid after negotiation had been different to the originally agreed
amounts. In the case of nine shipments the amount actually paid had been
less than the original amounts and in the case of the remaining nine,
it had been more than the originally tendered amounts. After balancing
out the losses against the gains, they had calculated that a sum of
USD 287,029 had been gained by the Sri Lankan government. The problem is
that this study on coal procurement carried out in 2015 and 2016 to
determine whether there was ‘loss or damage’ to the government has not
dealt with the most essential question.
This whole controversy arose in the first place, because the coal tender
had been awarded to Swiss Singapore Ltd after changing the bidding
criteria so as to accept the more powdery coal. One of the contentions
that Nobel Resources made in their petition to the Supreme Court was
that serious environmental damage would result from importing the more
powdery coal – a point that the Perera Committee has also accepted as we
saw earlier. Yet the Perera committee has argued perhaps tautologically
that the government had saved USD 287,029 (around Rs. 42 million) in
monetary terms by buying cheaper, lower quality coal from Swiss
Singapore Ltd. The question that we have to ask ourselves is whether a
paltry benefit of Rs. 42 million is adequate compensation for the
environmental damage caused. It is worthy to note that the committee
itself has recommended that the government should have suitable criteria
regarding the granular size of the coal in future tenders. It should be
borne in mind that the contract awarded to Swiss Singapore Ltd was for
three years during which lower quality coal would continue to be
imported.
The very terms of reference given to the Perera committee were loaded in
such a way that the yahapalana government would get the conclusion they
wanted from it. According to minister Ranjith Siyambalapitiya’s letter
to Prof. K. K. Y. W. Perera inviting him to chair the committee, the
only matter they were asked to look into was whether the government had
suffered any monetary loss due to the way coal was purchased after the
present government came into power. After thus appointing a committee to
state the obvious that there was a monetary saving by buying cheaper,
lower quality coal, and thus trying to convince the public that there
was nothing wrong with the manner the new government procured coal, the
government is now trying to devise ways and means of keeping Swiss
Singapore Ltd as the main supplier of coal despite the Supreme Court
ruling.
Bending the law
The Minister of Power and Renewable Energy has written to the Attorney
General requesting advice on how the Supreme Court decision should be
implemented. The Attorney General’s Department has written back that
while dismissing the application made by Noble Resources Ltd, the
Supreme Court has observed that there were ‘flaws’ in the decision to
award the tender to Swiss Singapore Ltd. The SC had stated that the
court had no alternative but to declare the decision to award the tender
to Swiss Singapore was ‘invalid in the eye of the law’ and that the
decision of the Standing Cabinet Appointed Procurement Committee in that
regard was outside its jurisdiction and, therefore, ‘null and void for
all purposes’. Furthermore, the SC had said that the decision taken by
the Cabinet to award the contract to Swiss Singapore Ltd ‘cannot be
considered a valid decision’.
Despite these observations, the AG stated that the SC did not make any
order to cancel the agreement entered into with Swiss Singapore Ltd. The
AG has covered himself by saying that in view of the adverse comments
made by the SC ‘it may be appropriate’ to terminate the agreement with
Swiss Singapore after giving adequate notice in terms of that agreement.
But in the same breath the AG says that any move to abrogate the
agreement without a court order could result in arbitration proceedings,
and claims for damages. The AG has advised the Minister of Power and
Renewable energy that he should apprise the cabinet of the options
available and the possible repercussions of terminating the tender and
to decide whether the tender should be cancelled after giving adequate
notice or whether fresh tenders should be called after the contract with
Swiss Singapore expires in April 2017.
Finally, the AG has advised that if a decision is made to terminate the
contract that it should be arrived at after a discussion with Swiss
Singapore Ltd to avoid costly arbitration proceedings. The funny thing
here is that this case was filed in the Supreme Court by Noble Resources
Ltd, against the Minister of Power and Renewable Energy saying among
other things that he had misled Cabinet into awarding the contract to
Swiss Singapore Ltd and the AG defended the Minister of Power and Energy
in that case. The SC gave leave to proceed in this case only because
they determined that there was a matter of public interest involved and
they deliberately refrained from dismissing it on the grounds of the
lack of locus standi of the petitioner to file such a case.
Though they dismissed the case, in the course of the judgement, the SC
held among other things that the tender had been improperly awarded to
Swiss Singapore Ltd which in fact was also the contention of the
petitioner. Now the main respondent in that case obtains advice from the
AG who defended him in court about how to work around the SC ruling! On
top of it all the main respondent also appoints a Committee of experts
asking them a tautological question whether the government received a
monetary benefit when the tender criteria was lowered and cheaper coal
obtained! The idea seems to be to retain the coal supplier selected by
the yahapalana government by hook or by crook. By observing the moves
made by the government in relation to the coal tender a clearly
identifiable way of doing things becomes apparent, which this government
has applied not only to the coal tender but to other matters as well.