A Brief Colonial History Of Ceylon(SriLanka)
Sri Lanka: One Island Two Nations
A Brief Colonial History Of Ceylon(SriLanka)
Sri Lanka: One Island Two Nations
(Full Story)
Search This Blog
Back to 500BC.
==========================
Thiranjala Weerasinghe sj.- One Island Two Nations
?????????????????????????????????????????????????Friday, September 9, 2016
CEB In A Quandary
- As Lack of Electricity by 2020 looming over the country
By Ifham Nizam-Thursday, September 08, 2016
The Ceylon Electricity Board (CEB) would lose more than USD 135 million
if they continued the work of Sampur Coal Fired Power Station, as they
would not be in a position to start its commercial operations before
2020.
The
additional cost for carrying out the project was estimated by the CEB
Transmission and Generation Planning Branch and had spelled out to the
CEB Board of Management.
Considering the probable power shortage after 2017 in the country, the
Board was keen in the long term power generation plan, and they were to
add power to the national grid through the 500MW Sampur plant at the end
of 2017.
Senior engineers from the Trincomalee Power Company Limited (TPCL), and
the sources from the CEB told The Sunday Leader that they won’t be in a
position to kick start the project as planned due to financial
barricades.
A TPCL official said both parties (CEB and NTPC) should be blamed for their lackadaisical attitude.
He said that with the ongoing resettlement in the area, related problems
would be further aggravated. Citing examples he said, resettlement is
in the corridor where coal transportation is going to be taking place
which he termed would be a major problem.
He also said that following recommendations of the Central Environment
Authority (CEA) after the Environmental Impact Assessment (EIA), all
recommendations were submitted in June.
“After three months, the CEA comes out stating that two other
specifications should be looked into. This time the letter was not from
the CEA Director General, but from another division of the CEA. The DG
during the last discussions in June agreed that we should go ahead
without further delay. Legally they should have responded within 30
days, not after three months,” the official said.
However, he added that they had submitted their response for the latest queries as well.
The officials said if conditions are going to be scrapped to cut short
the timeframe against the usual procedure, then the CEB should bear
consequences.
Meanwhile, Ceylon Electricity Board Engineers Union (CEBEU) President
Athula Wanniarachchi told The Sunday Leader the Indian government was
influencing the Sri Lankan government continuously in last five to six
years to accept unfavorable conditions in their agreements.
He said NTPC is pushing for low efficiency Indian machinery which may be
lower than Chinese technology (compared to Norochcholai). From 1990,
the CEBEU pushed for European or Japanese technology. It may be bit
expensive initially, but it would benefit the country in the long run.
”We assume the NTPC is purposely delaying the implementation of the
Sampur power plant until the CEB face a serious panic situation with a
huge deficit of power, in which we have but to agree with any
unfavorable conditions imposed by the NTPC”.
The union sources strongly believe that it is a strategic mistake to
start a joint power plant with an Indian company. None of the countries
in the subcontinent like Nepal, and Bangladesh have gained anything from
the energy business with Indian companies.
CEBEU Chief also said that the Japan International Cooperation Agency
(JICA) (or Japanese government) is willing to give a loan for a better
plant, but unfortunately, the Sri Lanka government has not yet given a
suitable land for the project.
He also said the CEBEU expects to educate and help the new government on this issue.
The TPCL is a joint venture company – 50 per cent by the CEB and 50 per cent by the NTPC.
The TPCL is responsible for implementing and operating the proposed
250MWx2 coal power plant complex in Sampur. The estimated cost of the
project is USD 512 million.
It will comprise two 250MW generators, the power of which will be
transmitted to the national grid through high voltage transmission lines
from Sampur via Habarana to the Veyangoda Grid Substation.